Oldham Engineering Installations are pleased to announce that they have been awarded a mechanical installation contract from Dematic Ltd. for the JD Sports, Rochdale – New Despatch System Project.

The project started on Monday 13th April 2015 and will be running consistently for 17 weeks, ~82 days on site. During this time OEI will be completing the installation of the New Despatch System, using a team of 12 engineers at peak times in the programme.

Oldham Engineering Installations have been working with Dematic at JD Sports since the summer of 2011, when we assisted with the mechanical installation of the original conveyor system. Since then we have supported Dematic and JD Sports with system extension and modification projects such as; Picking Mezzanine Conveyors, Various System Enhancements and Additional Sorter Chutes.

The conveyor types and equipment, which have been installed as part of these projects, include but are not limited to the following:

  • • Roller & Belt Conveyors.
  • • Accumulation Conveyors.
  • • Curves & Junctions.
  • • Diverts & Merges.
  • • AmbaFlex Spiral Conveyor.
  • • Sortec Cross Belt Sorter.
  • • Chutes & Work Benches.

Oldham Engineering Installations always aim to build long-term relationships with our clients and their customers. Oldham Engineering Installations working with Dematic at JD Sports shows that trust; reliability and professionalism can lead to repeated business for our client and ourselves.

Date posted: June 9, 2015 | Author: | No Comments »